Published : 04 Oct 2024, 09:34 AM
Updated : 21 Aug 2026, 11:56 AM
The National Review Committee, formed by the Ministry of Power, Energy and Mineral Resources, will examine 11 contracts related to power supply, including those with India’s Adani Power and other companies.
In a press release on Thursday, the ministry said that the committee has summoned all documents related to the 11 power plants.
The interim government formed the committee to review the contracts executed under the Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act, 2010 (amended in 2021). All the contracts being reviewed were signed during the previous Awami League government.
The government also issued a public notice on Thursday, inviting complaints from affected parties to be submitted to the committee.
Experts have raised concerns, accusing the ousted Awami League government of prioritising its trusted allies and beneficiaries in these contracts, allowing them to secure excessive profits at the expense of national interests.
One of the contracts under review includes the nearly 1500 MW Godda Power Plant in Jharkhand, India, built by Adani Power.
The government has never publicly disclosed the terms of its agreement to purchase power from this plant. However, critics claim that the price of electricity bought from Adani has at times been double the price of electricity purchased from India through government-to-government (G2G) agreements.
The review list also includes Summit Group’s Meghnaghat 583 MW and Kodda 300 MW power plants, Paramount Group’s Baghabari 200 MW plant, the 100 MW plant in Patuakhali owned by former Chief Whip ASM Feroz, Orion Group’s Mongla 100 MW plant, Midland Power Company’s Ashuganj 150 MW plant, Doreen Power’s 162 MW plant in Manikganj owned by former Awami League MP Tahjib Alam Siddiqui, Beximco Group’s Sundarganj 200 MW plant, Intraco Solar’s Lalmonirhat 30 MW plant, and the jointly owned HDFC Sin-Power’s Sutiakhali 50 MW power plant.
After the fall of the government following the student and public protests, the interim government formed this National Committee on September 5 to review the contracts executed under the Quick Enhancement of Electricity and Energy Supply (Special Provisions) Act, 2010.
Retired Justice Moinul Islam Chowdhury of the High Court Division is serving as the chair of the committee.
The other members include Professor Abdul Hasib Chowdhury of the Department of Electrical and Electronic Engineering at BUET, former COO of KPMG Bangladesh and Fellow Chartered Accountant (FCA) Ali Ashfaq, economist and former Lead Economist of the World Bank Zahid Hossain, and Professor Moshtaq Hossain Khan of the Faculty of Law and Social Sciences at the University of London (Economics).