Five units at Ashuganj Power Plant, closed overnight after a fire, resumed operations on Wednesday.
bdnews24.com News Service
bdnews24.com
Published :
24 Mar 2010, 07:25 AM
Updated :
10 Aug 2022, 10:02 PM
Brahmanbaria, Mar 24 (bdnews24.com) — Five units at Ashuganj Power Plant, closed overnight after a fire, resumed operations on Wednesday.
Seven out of total eight units of Bangladesh's largest power plant had shut down at around 8.00pm Tuesday as a fire broke out in the transformer room.
One 150MW unit remained unaffected. Another 34MW unit resumed generation, at around 10pm, after repair.
Ashuganj managing director Abdul Khaleque told bdnews24.com that they struggled overnight and were finally successful in bringing the remaining five units back online.
The 723MW Ashuganj power plant accounts for more than a fifth of the country's current peak power production of about 4000MW.
Bangladesh's peak demand is around 52000MW.