Published : 24 Aug 2024, 11:00 PM
Updated : 21 Aug 2026, 11:48 AM
Construction work on the third terminal at Dhaka’s Hazrat Shahjalal International Airport is 98 percent complete, according to Monjur Kabir Bhuiyan, chairman of the Civil Aviation Authority of Bangladesh.
The CAAB chief visited the newly constructed check-in counter, immigration, scanners, boarding bridge, arrival, departure, aircraft parking apron and road network at the terminal and the other facilities built under this project.
He spoke to officials and employees involved in the project on the progress of the terminal, the quality of work, and the possibility of meeting the deadline for construction.
Stating that 98 percent of the terminal's work has already been completed, Monjur noted that this terminal has special importance as a gateway for economic growth and global communication of the country. Therefore, he stressed the importance of completing the remaining work on the terminal as soon as possible.