Published : 16 Nov 2024, 05:45 AM
Updated : 21 Aug 2026, 12:05 PM
Nepal has begun supplying electricity to Bangladesh through India’s grid, ending a six-year wait for the Himalayan nation’s hydropower to reach Bangladeshi consumers.
The transmission process was officially inaugurated on Friday at 12:55pm with virtual participation from officials of Nepal, India, and Bangladesh.
An official from the Power Grid Company of Bangladesh, or PGCB, confirmed that from 1:00pm, 38 to 40 megawatts of electricity is being supplied via the Bheramara grid, previously used for imports from India.
Data from the PGCB’s website showed a slight increase in power flow to the grid after the transmission began, with the total crossing 946 MW by 7:00pm.
Earlier, the transmission line had never carried more than 918 MW of electricity.
Power, Energy, and Mineral Resources Advisor Fouzul Kabir Khan told bdnews24.com, "Nepal’s electricity has started coming in, and perhaps in the near future, we will be able to bring in even more."
Discussions to import power from Nepal began six years ago. In 2018, a memorandum of understanding, or MoU, was signed between the two countries, but the power had to be transmitted through Indian grid lines, leading to extended trilateral negotiations.
Under the previous Awami League government, meetings were held to discuss the matter, but progress was delayed by bureaucratic hurdles from Indian authorities.
In June this year, while the Awami League was still in power, the Cabinet Committee on Government Purchases approved the purchase of electricity from Nepal through direct procurement.
The agreed rate was Tk 8.17 per unit, which is more cost-effective than Bangladesh's current domestic power production, which exceeds Tk 11 per unit.
In October, following the formation of an interim government, a tripartite agreement was signed in Kathmandu for the import of 40 MW of electricity.
The agreement involves the Nepal Electricity Authority, or NEA, India’s NTPC Vidyut Vyapar Nigam Limited, or NVVN, and Bangladesh’s Power Development Board, or PDB.
Under this agreement, power imports will continue for seven months annually, from April to November. Over five years, this will cost nearly Tk 1.6 million, with an annual expense of about Tk 1.3 million.