US ship 'TYCO Durable' to complete submarine branch route by June
The US ship 'TYCO Durable' has already installed 152 km submarine cable of 1,260 km branch route under the seabed in the Bay of Bengal.
bdnews24.com News Service
bdnews24.com
Published :
06 May 2005, 06:00 PM
Updated :
17 Aug 2022, 08:36 PM
Dhaka, May 7 (BDNEWS) - The US ship 'TYCO Durable' has already installed 152 km submarine cable of 1,260 km branch route under the seabed in the Bay of Bengal.
Bangladesh submarine cable project sources said laying 20 km cable a day, the branch route is expected to be completed by the first week of June.
Earlier, the American company TYCO, sub-contractor of Fujitsu, began cable installation towards the junction of the Singapore-France-bound cable under the Bay on April 29 from 14.5 km off Cox's Bazar, the point where Swisco-12 ended laying cables.
Engr Monwar Hossain, project director of Bangladesh Submarine Cable Project, said 'TYCO Durable' can work in the sea in any adverse weather.
The ship manned and equipped by over 70 experts from the USA, New Zealand, Britain and Australia, and a powerful 'gator' (robot), the PD said adding that the robot is doing the soil-cutting as well cable-laying works under 0.8m from the seabed.
Meanwhile, Fujitsu, the Japanese telecom platform, the main contractor for the project,