Submarine cable project testing begins this week amid un-preparedness of BTTB
The long-awaited testing of the SEA-MEWE4 submarine cable project at the Cox's Bazar landing station begins this week but Bangladesh Telegraph and Telephone Board (BTTB) has no preparation to get this job done properly.
bdnews24.com News Service
bdnews24.com
Published :
17 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:20 PM
Dhaka, March 18 (BDNEWS) –The long-awaited testing of the SEA-MEWE4 submarine cable project at the Cox's Bazar landing station begins this week but Bangladesh Telegraph and Telephone Board (BTTB) has no preparation to get this job done properly.
BTTB sources feared that it may jeopardise the very first test of the country's first submarine cable project.
The cable landing-station testing crew of Fujitsu and Alcatel are arriving on Monday; but BTTB has not installed essential power facilities, including rectifiers, generators and converters in Cox's Bazar.
The air-conditioning system, a fundamental requirement of such critical exercise, is also yet to be installed.
Now the BTTB authorities are hastily dismantling obsolete power systems of the old installations and dumping those at Cox's Bazar as proxy solutions to test the highly sophisticated landing station equipment.
Concerned BTTB officials are sceptic about the proper test results due to BTTB's piecemeal arrangement.
The sources blamed BTTB's chairman and the concerned project director for such failures as they wasted about nine months to process the bids of Chittagong-Cox's Bazar optical fibre cable project.
Power supply and air conditioning systems are the integral components of this project, the sources added.
Currently the cabinet purchase committee has been reviewing the offers of Siemens (Tk 47.42 crore) and Nortel (Tk 30.72 crore) for this project.
This high-powered body, headed by the finance and planning minister and composed of nine cabinet members, is meeting Saturday to select the winning bidder followed by recommending for the prime minister's approval.
Instead of waiting for that decision, the BTTB has isolated the power supply works of the Chittagong-Cox's Bazar link project and invited local bids separately. Sources say that the supply the power system is an integral part of the undecided bids of Siemens and Nortel.
It prompted Nortel to lodge complaints with the central procurement technical unit (CPTU) of the planning commission. The CPTU, in its letter to the telecom ministry, has objected to BTTB's such bidding for the partial works of a project, which has been waiting for the highest authority's approval.
The CPTU has also said that BTTB's such move violates the public procurement processing and approval procedure.
Highly placed sources said all the above issues are like to dominate Saturday's meeting of the cabinet purchase committee.
BDNEWS/1927 hrs