Dhaka, Oct 9 (bdnews24.com) – The health ministry committee investigating into the alleged misuse of government's funds in the ICDDR,B's expansion project will submit its report shortly.
Convenor of the committee S M Ashraful Islam, joint secretary (administration), told bdnews24.com on Sunday that they were in the final stages.
"It's (the investigation) document based. We were required to scrutinise many documents," he said, adding they had to extend their time beyond the two-month schedule.
"But now we are ready. (We) will submit it shortly," he said.
The ministry formed a four-member committee in July 3 to look into the use of its Tk 1-billion fund, which was disbursed in three parts to complete vertical expansion of the Centre's three-storey Mohakhali building into eight-storey by 2009.
But the project started in March 2006 could not be completed and came to a halt, raising questions on the way the project was executed.
In view of certain complaints, a health ministry notification earlier stated that the ministry felt it imperative to look into the matter 'to ensure transparency and accountability'.
The document circulated to the officials concerned said that even though ICDDR,B could not complete the expansion of the initial projects, new projects were approved on the Centre's proposal.
It was alleged that ICDDR,B wasted much of the fund by not following 'the sequence' of the construction work. They bought various items which were supposed to be bought at the end of the construction work. Those items had lost the guarantee period, it was charged.
Besides, some of its officials visited a number of countries like Japan, Germany, the UK and the USA at suppliers' cost even before selection of bidders for buying necessary materials and equipment.
The committee was asked to look into all these aspects, according to the terms of reference (TOR) of the committee.
The TOR reads, "Whether logical sequence or critical paths were followed in implementation of the project or activities; for example whether things that could not be used before actual physical construction were procured, and if so, on what basis?
"Whether officials of Finance and HR departments were sent abroad with suppliers' fund even before selection of the bidders and has it compromised the procurement?"
The committee was also asked to dig into other issues 'related to the implementation of the projects or activities disbursed to ICDDR,B from the government of Bangladesh'.
An ICDDR,B official earlier told bdnews24.com that they were worried about the reputation of the centre, as it had not been 'well-managed' at least in the last five years.
Recently the Centre has taken off meat, fish and egg from patients' diets to cut costs amid allegations of prohibitive salaries for some of its foreign officials and corruption.
The only centre of its kind in the developing countries, ICDDR,B was set up through an ordinance in 1978.
The government is the largest donor of the centre which receives about Tk 100 million donations annually. It has been also given immunity from local taxes, rates and duties.
The centre also enjoys a legal mandate for movement of biological materials in and out of the country.
Deputy chief (family welfare) Mohammad Helal Uddin, deputy secretary (admin-3) Mohammed Alfaz Hossain and executive engineer of the Health Engineering Department's Dhaka Division Mohammed Golam Haider Khan are the other members of the committee.
bdnews24.com/nih/nir/1725h