Published : 14 Mar 2016, 01:20 AM
Updated : 11 Apr 2022, 09:44 PM
At a media briefing on Sunday, he said the process was on to sign a deal with Malaysia to build a power plant with the capacity to produce 1000-1300 megawatt electricity.
Another plant is being discussed with China, he said while speaking with journalists after a meeting on power plant affairs at the ministry.
“We have given the ‘go ahead signal' with Malaysia. Now the deal will be signed. We've also given another conditional go ahead for the other plant and are now negotiating with China.”
The minister said the deal with Malaysia was fixed at 50-50 share and they were also trying to keep the same terms and conditions with China.
Mentioning that both plants will be set up in Maheshkhali, Muhith said, "Maheshkhali will be the power hub."
India wants date for Payra deal
Prior to the media call, the finance minister met Indian High Commissioner Harsh Vardhan Shringla on Sunday.
Referring to the meeting, he told reporters that a power plant may be set up at Patuakhali's Kolaparha before building the Payra Port there.
"You (journalists) have may get good news within a month. We may strike a deal for the power plant there. Today, they (India) asked me for a date to sign the agreement."
He said this plant may also have the capacity to generate 1200-1300 MW electricity.
Asked whether India would join the Payra Port project, Muhith said, "I can't say anything about that now. Currently, China is discussing with us. But India is interested, too. However, China has already made the official offer."
The minister said he also discussed with the Indian high commissioner about importing 100 MW more from Tripura.
After the tender process is completed, it will not take more than three years to finish the Rampal power plant project, he added.