Published : 05 Jan 2016, 03:22 PM
Updated : 08 Aug 2022, 03:31 PM
The Executive Committee of the National Economic Council (ECNEC) cleared the sum at its meeting, chaired by Prime Minister Sheikh Hasina, on Tuesday.
Planning Minister AHM Mustafa Kamal said ‘several new components’ had been added to the project.
“The expenditure soared as cost of river training went up and more land had to be acquired,” he told the media after the meeting.
The minister expects the bridge to be opened to traffic in December, 2018.
“It is a dream project for the entire nation. When constructed, it will increase the GDP growth rate by 1.5 percent,” he said.
Project Director Shafiqul Islam had earlier told bdnews24.com that expenditure in excess of estimates for river training work and two phases of the main bridge construction had led to the cost escalation.
Prime Minister Sheikh Hasina launched the construction of the main structure on Dec 12. The 6-km-long bridge will connect the country’s southern region with capital Dhaka.
The planning ministry had estimated the bridge cost to be about Tk 205 billion, to which Tk 82 billion is now being added to see the project through.
China Major Bridge Engineering Company is building the main structure at a cost of Tk 121 billion. Sino Hydro Corporation is being paid about Tk 87 billion for river training.
The estimated cost for the two phases in 2011 was Tk 91.72 billion and Tk 53.62 billion.
Planning ministry officials said the construction of roads linking Jajira and Mawa with the bridge and service roads had also over shot initial estimates.
The expenditure incurred for the three project components have been Tk 10.97 billion, Tk 20.8 billion, and Tk 1.93 billion.
The three segments of the project are being jointly executed by Abdul Monem Ltd of Bangladesh and Malaysia’s HCM Construction.
The ECNEC had approved the multipurpose project at a cost of Yk 101.61 billion in 2007.
Subsequently, the cost was revised upwards following a change in the bridge design. In 2011, the ECNEC cleared a Tk 205.07 billion project plan.