Published : 19 Jan 2016, 04:44 PM
Updated : 19 Oct 2022, 05:04 PM
A meeting of the Executive Committee of the National Economic Council (ECNEC) chaired by the prime minister on Tuesday also approved another Tk 4.47 billion for the project, raising the cost by almost 58 percent.
Planning Minister AHM Mustafa Kamal told a media briefing that the cost of the project was estimated at Tk 7.72 billion, which now has gone up to Tk 12.19 billion.
He said the matter of underground utility supply ducts for gas, electricity, water, and fibre optic cables were not taken into consideration when the project was initiated.
“In addition, an extension of the flyover from the FDC entrance to Hotel Sonargaon in Karwan Bazar and the installation of earthquake resistant technologies have also hiked the cost,” added Kamal.
The flyover’s length will now be extended by 450 metres, making it 8.70 kilometres long. It will now end near Hotel Sonargaon in Karwan Bazar instead of the FDC entrance.
The deadline to complete the work has also been re-fixed to June 2017, the minister said.
“But this deadline will not be extended anymore, the prime minister has said. Once this project is finished, traffic jam on the Moghbazar-Mouchak-Saat Rasta route will decrease.”
The flyover is being built in three parts — from Moghbazar to Tejgaon, from Kakrail to Rampura, and from Mouchak to Banglamotor.
Approved in 2011, the construction of the project started in 2013 and since then the tenure has been extended twice.
The Saudi Fund for Development and the OPEC Fund for International Development are financing the scheme.
Development agencies were supposed to fund Tk 5.72 billion, but now they have agreed to increase it to Tk 7.76 billion.
The government has also increased its financial commitment for the project from Tk 2 billion to Tk 4.42 billion.
Nine other projects cleared
Apart from the Moghbazar-Mouchak flyover project, the ECNEC on Tuesday also greenlighted nine other projects at a cost of nearly Tk 83.31 billion.
Of that, a little over Tk 36.03 billion will come from the government exchequer while the organisations concerned will contribute more than Tk 4.51 billion from their own funds and over Tk 7.76 billion will come as project assistance.
These projects include development of power distribution system in Rangpur, LED Light (CKD) assembling plant in ETL, construction of residential buildings for the Supreme Court judges, Nilphamari-Jaldhaka road development, establishment of Shaheed M Mansur Ali Medical College and 500-bed Hospital in Sirajganj, the second phase of Small Farmer Development Foundation
Assistance, and the first phase of development of Cox's Bazar Airport.