According to him, there will be tenders for three types of construction works including the core structure of the Padma Multipurpose Bridge.
At a pre-budget discussion on Tuesday with the Economic Reporters' Forum (ERF), Abul Maal Abdul Muhith said work for the project’s tender would start from where it got stuck.
“Tenders for constructing the main bridge, river training and consultancy work will be floated within next month (May). If delayed, the process could spill over into the first week of June,” Muhith said.
He said a ‘blacklisted’ company would be excluded from the tender process.
The minister said the government had already approved tenders for constructing a connecting bridge at Jajira Point. A contractor for the Mawa Point would be appointed soon, he added.
Muhith reiterated the government would construct the bridge with its own funding, but he said if the Japan International Cooperation Agency (JICA) and Asian Development Bank (ADB) so wished, they would be welcomed back in the project.
Both the ADB and the JICA pulled out of the project on Feb 2 after the government retracted its request for funding to the World Bank. The two together were to provide $1 billion for the project.
The Washington-based lender and the government locked horns over corruption allegations on awarding the project consultancy.
Finance Minister Muhith said Tk 23 billion had been allocated in the budget for the current financial year.
He said Tk 68 billion would be allocated in the 2013-14 fiscal, Tk 78 billion in 2014-15 and Tk 50 billion in the 2015-16 fiscal for the construction of the Padma bridge - Bangladesh's biggest-ever infrastructure project.
Muhith went on that $200 million Indian grant had been set aside for the project and added that it would be possible to collect another $1 billion from the international market through sovereign bonds.
He said the design of the bridge would have to be ‘slightly altered’ due to the loss of time.