Saifur to talk with low-performing ministries on ADP implementation
Finance and Planning Minister M Saifur Rahman would sit separately with the ministries that have performed badly in implementing the annual development programme (ADP) in the first five months of the current fiscal.
bdnews24.com News Service
bdnews24.com
Published :
17 Jan 2006, 06:00 PM
Updated :
17 Aug 2022, 05:42 PM
Dhaka, Jan 18 (BDNEWS) - Finance and Planning Minister M Saifur Rahman would sit separately with the ministries that have performed badly in implementing the annual development programme (ADP) in the first five months of the current fiscal.
Saifur after a review of half-yearly ADP implementation told reporters Wednesday that the performance was not satisfactory, although some improvements were made compared to the previous year.
The meeting was held at the NEC auditorium with Saifur Rahman in the chair. Secretaries of the concerned ministries were present.
The top five prioritised sectors in the ADP are – education and religion (13.46%), followed by power (12.73%), rural development (12.23%), transportation (12.20%) and health (9.26%).
"The minister will sit soon with some selected ministries, such as Energy, Communication and Power that have shown dismal performance in implementing the ADP during July-November period," a senior official of the Planning Commission told BDNEWS.
Saifur expressed satisfaction saying 33 percent of the allotted ADP expenditure has been spent during July to December of 20005-06, which was only 23 percent in July-November period.
This implementation rate needs to cross 50 percent by February, hardly March, to achieve the target, the minister told reporters.
According to data of the Planning Commission, 15 ministries, which are to implement more than 75 percent of Tk 24,500 crore ADP, completed only 23 percent of the work during the period by utilising local resources, while the rate of implementation of the foreign funded project is 22 percent.
These 15 ministries that include communications, shipping, local government, rural development and cooperatives, health and education are responsible for implementing 635 projects out of 859 ADP projects. The cost of these projects has been estimated at over Tk 19,200 crore.
The other ministries and divisions, which are assigned to implement nearly 25 percent of the ADP works involving over Tk 5,200 crore, have completed seven percent and five percent of the works of local and foreign funded projects respectively during July to November of 2005-06.
Power Ministry was allocated Tk 3,212.5 crore in the ADP. Of which, the ministry spent only Tk 718 crore (22 percent) in July-November period, officials said, adding the communication ministry used Tk 441 crore out of an allocation of Tk 3131 crore during the same period.
Poor institutional capacity, delay in release of foreign funds and delay in disbursement of allocated funds by the line ministries are blamed for the slow pace of ADP implementation.
Earlier, in the first month of the current fiscal, the government decided to review the ADP jointly by the planning and finance ministries on a monthly basis instead of a quarterly basis to expedite implementation.
BDNEWS/1831 hrs.