November 23, 2026

Production resumes in Ashuganj plant

Power generation in four units of Ashuganj Thermoelectricity Plant has resumed after 44 hours of disruption.

bdnews24.com News Service

bdnews24.com

Published : 09 Apr 2011, 12:48 PM

Updated : 10 Aug 2022, 04:37 PM

Brahmanbaria, Apr 9 (bdnews24.com) — Power generation in four units of Ashuganj Thermoelectricity Plant has resumed after 44 hours of disruption. Four of the six units that had tripped on Thursday morning for technical problems were repaired and those went into production around 5pm on Saturday, plant managing director Nurul Alam told bdnews24.com. The four units have a capacity of 296 megawatts. The No. 2 unit and No. 5 unit, of 64 MW and 150MW capacity are undergoing overhaul, Nurul Alam said. Two other units in the plant have been closed for three months for a major overhaul. bdnews24.com/corr/qh/ra/pd/sh/mr/1845h
Related Stories