The Power Secretary is hopeful that imported power from India would be added to the national grid by then. Reazul Bashar reports. Updates
bdnews24.com News Service
bdnews24.com
Published :
20 Jul 2012, 03:08 PM
Updated :
09 Aug 2022, 04:01 PM
Reazul Bashar
Senior Correspondent
Bheramara, Kushtia, Jul 20 (bdnews24.com) — A top government official has expressed optimism that around 500 megawatts of electricity would be added to the national grid by July next year.
"Forty-five percent work of the inter-country transmission line on Bangladesh side and grid substations has been completed," Power Secretary Abul Kalam Azad told reporters while on a visit to an inter-country grid substation here on Friday.
"I am hopeful that the national grid will be fed another 500 MWs of electricity, purchased from India, by July next year as the construction work is likely to end by then," he added.
The Power Secretary pointed out that the government had already signed a deal with India to import 250MW electricity and was planning to sign one more deal to purchase another 250 MW from the neighbouring country.
Aiming to meet the growing demand of electricity, Bangladesh inked a Memorandum of Understanding (MoU) with India in 2010 to import 500 MWs of power.
Later in Feb this year, the Power Development Board (PDB) signed a deal with India's National Thermal Power Corporation (NTPC) to purchase 250MW electricity.
Azad said the rest 250 MWs would be obtained from other Indian power plants as 'procedure is underway' for the same.
Per unit imported power will cost Tk 4 to Tk 4.50, he added.
Construction work of the inter-country sub-station grid is going on in full swing on 113-acre of land at Golapnagar of Bheramara Upazila in Kushtia district adjacent to Hardinge Bridge at an estimated cost of Tk 11 billion.
Project Director Kazi Ishtiaq Hasan told reporters that as many as 78 towers would be installed over a 27-km stretch in Bangladesh territory for power transmission. Of which, foundation work of 61 towers have already completed while that of the remaining 17 is underway.
The Power Secretary said that the construction work on 79-km power transmission line on the Indian side was also in progress.
After the execution of the 400KV Bangladesh-India power grid line inter-connector project to import electricity from across the border, it will be possible to bring power up to 1,000MW power through the transmission line.
Saying that the government plans to import more power through the transmission line, the Power Secretary said, "The transmission line can also be used as regional grid line in importing power from Nepal and Bhutan in future."
According to government statistics, the daily demand has been limited to around 6,500 MW through 'Demand Side Management' though the real demand is almost 7,500 MW.
PDB says the power production was 6,186 MW against the demand of 6,100 MW on Thursday.
He said the incumbent government inked several agreements for 56 power plants under both private and public management, and added that 29 of those plants had started operation.
According to PDB, the daily power production increased by 3,500 MW due to installation of new plants during the tenure of the incumbent government.