Multifarious problems grip prospective limestone, cement projects in Joypurhat
In Joypurhat there is a reserve of 270-million metric ton limestone at a depth of 518-549 metres from the surface, from which 45 to 55 percent can be extracted.
bdnews24.com News Service
bdnews24.com
Published :
04 Mar 2006, 06:00 PM
Updated :
17 Aug 2022, 05:54 PM
Joypurhat, Mar 5 (BDNEWS) – In Joypurhat there is a reserve of 270-million metric ton limestone at a depth of 518-549 metres from the surface, from which 45 to 55 percent can be extracted.
According to the project proposal submitted by German Messrs Froid Krup Rostaf in 1966-67 a total of 1.44 million metric ton cement can be produced from 1.65 million metric ton limestone every year. Pakistan government took the initiative to materialize the project but failed to operate for financial constraint.
In 1974 during Bangladesh era the project appeared to run with government approval but was slipped on the way for mismanagement.
Depending on a deal signed between Bangladesh and Saudi development fund worth Tk 3 crore in 1979 Cementation Mining Ltd of Britain got a contract in 1981 through an international tender.
But once again, the project fell into a gridlock as breaking the condition the contractor firm demanded twice the real price.
The project proposal worth Tk 908 crore was approved again in 1983. Bangladesh met its counterpart Saudi development fund and Kuwait fund twice later in 1984 and '86. But the trilateral meeting came to no effect.
In July 1994, the project got financial assurance from Polish firms Copex, Polymex and Cikop.
Petrobangla tabled the proposal of whether to take the loan on condition or not in its 171st meeting.
Petrobangla allegedly did a mere presentation of minimal information about the reserve, the position of limestone and the potential of the project.
Petrobangla was informed through a geological study that the limestone deposit was not available at the near surface level.
Later Petrobangla was instructed to handover the project to private sector and the period was extended till 2004. Still the project remains in an endless snarl-up.
Currently the Joypurhat cement complex has been left abandoned for long and some 15 buildings including 57 acres of land for the establishment of a Girls' Cadet College, 10.53 acres of land to Kishore Unnayan Kendra, 5 buildings for the Institute of Mining, mineralogy and metallurgy project and 29 acres of land for the Deputy Commissioner have been allocated.
The project now exists on paper rather than in reality with 29.77 acres of land, idle officials, office buildings with 65 lakh bricks, 204 metric ton rod, 28 thousand cubic feet brickbats, 340 metric ton coal and other 356 types of construction materials.
A total of Tk 66 crore has already been spent materializing the project without result.
Meanwhile, thousand acres of land remained uncultivated in the project site. Joypurhat locals demand launching of the project with local technology without delay.
BDNEWS/0919 hrs.