India clears Lafarge to resume mining for Chhatak
India's Supreme Court allows the French multinational to mine limestone at Nongtrai, paving way for resumption of supply of raw materials to the cement plant in Bangladesh
bdnews24.com News Service
bdnews24.com
Published :
07 Jul 2011, 09:58 AM
Updated :
10 Aug 2022, 05:04 PM
New Delhi, July 7 (bdnews24.com)—The 17-kilometer-long conveyer belt from the north-eastern Indian state of Meghalaya to the cement plant at Chhatak in Bangladesh is set to restart ferrying limestone across the border.
Lifting a ban it imposed 17 months back, India's Supreme Court has allowed French multi-national Lafarge to resume limestone mining at Nongtrai in East Khasi Hills district of Meghalaya, paving the way for resumption of supply of raw materials to the cement plant at Chhatak.
A three-member bench of the Supreme Court headed by chief justice of India S H Kapadia upheld the legality of the 2010 clearance by the India's Ministry of Environment and Forest to the Lafarge for limestone mining at Nongtrai.
The court dismissed an appeal filed by Shella Joint Action Committee, a local organisation of environmentalists, challenging the MoEF clearance and Environmental Impact Assessment that favoured mining.
India's apex court had in Feb 2010 halted limestone mining by Lafarge Umiam Mining Private Limited or LUMPL in Meghalaya. The LUMPL is a wholly owned subsidiary of the Lafarge Surma Cement Limited or LSCL.
The LUMPL had earlier been transporting limestone mined from Nongtrai to the cement plant of the LSCL and Spanish company Cementos Molins at Chhatak by a 17-kilometre long cross-border conveyer belt. The LSCL plant at Chhatak has a capacity of producing 1.5 metric tonnes (MT) cement every year.
Indian government had on Mar 24 last year told the Supreme Court that the latter's order halting mining and supply of limestone from Meghalaya to Lafarge's cement plant in Bangladesh is disturbing the bilateral relation between the two neighbours.
India's attorney general G E Vahanvati had told the court that the order to halt limestone mining had hit production at the Lafarge's US $ 255 million state-of-the-art plant at Chhatak.
The MoEF had told the Supreme Court that Lafarge would pay up Indian Rupees 72.66 crore at 9 percent interest from April 1, 2007, which would work out at Indian Rupees 88 crore.
In addition, it would pay the government of Meghalaya Indian Rupees 90 for every tonne of limestone mined from the state since 2007, which would work out at around Indian Rupees 45 crore.
Allowing LUMPL to resume limestone mining in Meghalaya, the Supreme Court also issued a set of guidelines for the Indian government to go by while issuing environmental clearances for projects in forest areas.
The special forest bench of the Supreme Court had halted mining, acting on a petition of the SJAC, which alleged that exploitation of natural resources by Lafarge at Nongtrai was posing a threat to environment and changing rainfall pattern in the ecologically fragile area.
Nongtrai is in the vicinity of Cherrapunji, which once received maximum rainfall in the world and was known as the wettest place on earth.
The SJAC had filed a lawsuit alleging that rainfall in and around Nongtrai had come down due to large-scale denudation of forest caused by limestone mining by Lafarge.
The Bangladesh government on March 2 last year written to the Indian High Commissioner in Dhaka expressing concern over Supreme Court's ban on mining of limestone and consequent disruption in supply of raw material to the cement plant at Chhatak.
The Lum Mawshun Minerals Private Limited had first got the clearance for the mining project from the forest department of the state government of Meghalaya.
The clearance was transferred to the LUMPL in 2002. But the clearance given to Lum Mawshun Minerals Limited came under doubt after the state government's Chief Conservator of Forest in 2007 noted that the mining project was located in the midst of natural and virgin forest.
bdnews24.com/corr/bd/1520h