Unocal starts Bibiyana gas field development
Unocal has started development works of the much-talked-about Bibiyana gas field in Habiganj.
bdnews24.com News Service
bdnews24.com
Published :
31 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:25 PM
Dhaka, Apr 1 (BDNEWS) – Unocal has started development works of the much-talked-about Bibiyana gas field in Habiganj.
With an expected investment of US$ 230 million, the company will drill up to 15 wells in the field, develop three processing plants and set up pipelines for supplying gas to the national grid.
Beside, the company will have to develop roads in the locality as the gas field is situated in a remote low land.
"On completion of earth filling and other necessary works, the drilling is expected to be commenced in October this year," said a top official of the US oil company.
The Unocal has already signed a GPSA (gas purchase and sale agreement) with state-run Petrobangla to develop the Bibiyana field, discovered in 1998.
The field is expected to add 200 MMCFD (million cubic feet per day) of gas beginning in the fourth quarter of 2006.
Unocal estimates that the Bibiyana field could ultimately produce 500 MMCFD by the end of 2009.
The US company had once approached exporting gas from the field having a reserve of over two TCF (trillion cubic feet) to India.
But, the proposal was turned down amidst huge political opposition.
The company also faced difficulties in beginning development work of Bibiyana as local people built up a movement demanding a compensation of Tk 1.5 million for each acre of land, gas supply to the locality and employment of local youths.
Sources concerned said that the locals in a recent meeting at the office of deputy commissioner agreed to lower the amount of compensation to Tk 500,000. Unocal also agreed, the sources added.
The Unocal currently supplies approximately 200 MMCFD of gas from its Jalalabad field in Sylhet and over 70 MMCFD from Moulvibazar field.
With production started from two wells in Moulvibazar in third week of March, Prime Minister Khaleda Zia is expected to formally inaugurate the plant on April 5.
The Unocal plans to complete two more wells in Moulvibazar by May 2005 increasing the field's production capacity to 150 MMCFD.
BDNEWS/1510 hrs