The grid was still at risk, said Nasrul Hamid Bipu at the Secretariat on Wednesday while discussing the probe report on the Nov 1 countrywide blackout.
Automated systems to control load on feeders that distribute power would be put in place, but that would take time, he said.
“The blackout happened because of under-frequency since it could not balance out with the demand.”
The state minister had earlier cited internal technical flaws within the grid for the collapse.
File Photo
“Penalties will not work, resources must be developed,” he said when asked if any persons would face measures for the grid failure.
“Power load must be controlled with automated systems. Problems occur when they are handled manually.”
“There are some archaic systems in our power plants, several of their clocks are not synchronised with GPS.
“Sometimes phone calls are made manually to control fluctuating frequency, they trip if not shut down in time.”
The junior minister said the work to move towards an automated system had already begun.
“More time is needed… we are trying to see how the technical faults can be fixed.”
As for the state of the National Grid, he said, “To sum up, they are still at risk. I thank our people because of the risks they must work with. We must head for automation fast – so we are working on it.”
Asked whether errors in the planning caused the situation, he said it was not a policy mistake - there just was not enough time to keep up with the developments.
The investigation committee made 22 short-term and 10 middle and long-term recommendations.
Power Secretary Monwar Islam told reporters to avoid such problems, an automated system must be installed to control load on feeders. "We are working on that, but it will take time."
The power transmission line in Kushtia's Bherhamara, through which Bangladesh imports power from India, reportedly snapped on Nov 1, triggering the over eight-hour-long blackout.
The glitch had stopped power supply from the transmission line to the National Grid when all power plants in the country had ceased generation.
The government had formed a seven-strong committee to identify the cause of the biggest power outage in recent memory.