SPECIALSidr rehabilitation work sluggish
The rehabilitation project, financed by World Bank, for the cyclonic storm Sidr-hit people seems to be moving at a very sluggish pace.
bdnews24.com News Service
bdnews24.com
Published :
18 Nov 2010, 06:59 AM
Updated :
24 Apr 2022, 05:47 PM
Moinul Haque Chowdhury
bdnews24.com senior correspondent
Dhaka, Nov 18 (bdnews24.com)—The rehabilitation project, financed by World Bank, for the cyclonic storm Sidr-hit people seems to be moving at a very sluggish pace.
Even after almost three years since the devastating storm hit the coastal areas of Bangladesh, the progress of the rehabilitation moves only to a call for tenders.
Officials of the project and the Planning Commission also admit that not much has been achieved since the project was taken up.
Planning has been made for the construction of only 300 shelters for the affected people, as both the guarantor, World Bank, and the Bangladesh government are moving lethargically. It is only recently that the tenders were called for the project.
While points have been selected for revamping and construction of a 480-kilometre dam to avert further disasters, the sites are still being evaluated by the consultants.
The cyclone that hit the low-lying coast of southern Bangladesh on Nov 15, 2007, with winds of over 230 km/h, was the deadliest storm to hit the country in more than a decade.
Long after surviving the aftershocks of Sidr, 22 upazilas in that area was swept over by another apocalyptic tornado, Aila, on May 25, 2009, causing widespread damage and affecting around three million people.
The government approved the Emergency 2007 Cyclone Recovery and Restoration Project (ECRRP) to reconstruct the infrastructures in the affected areas.
Some dissatisfied Planning Commission officials said that construction works of 50 shelters are yet to start, even though the Tk 75 million-project had already been approved.
A joint survey consisted by World Bank and other development associates—(Joint Damage Loss and Needs Assessment-JDLNA)—estimated the total cost of damages at $115.6 billion.
As the World Bank showed interest in extending its hands, the Bangladesh government approved a Tk 7.5 billion ($109 million) project.
Mohammad Abdur Rauf, deputy secretary to the government and ICRRP director, told bdnews24.com, "The project and its approval took much time. The overall process is under progress now. Places have been selected for construction of the shelters and tenders have been called for the future works."
Rauf added, however, that they were not satisfied with the job by the Water Development Board (WDB) in reconstructing the dam.
"The Local Government Engineering Department and Disaster Management Bureau is working hand in hand, in line with a guideline, while building the shelters. There are some developments in the project's agriculture, fishery and animal resources sectors, but nothing notable could be done in building the dam," he added.
The project director, however, seems hopeful that the project could be brought to a successful conclusion by June, 2013.
Criticising the lack of coordination in the WDB, the official said, "Full fledged work will start soon. The locals will be benefited before the next rainy season."
Rauf, who is also the director of World Bank-financed project—Coordination and Monitoring Unit (PCMU)—said the deal with the World Bank on the financial aid had been signed in November 2008. The JDLNA report required six months for submission, and another 11 months passed devising the project and getting it approved.
Once the project was given the green signal, however, almost a year passed before its implementation began, explained the project supervisor, rationalising on how the first two years had passed.
A third year was spent in designing the project, appointing consultancy firms in line with World Banks policy and government Public Procurement Rules (PPR), collecting necessary equipment and vehicles, and calling tenders, he added.
Seven agencies have been employed to execute eight sub-projects under the ECRRP project. The Local Government and Engineering Department (LGED) will carry out a Tk 2.9 billion sub-project to renovate 250 old shelters, construct 50 new shelters, 30 forts, and the necessary roads which will lead to the shelters.
The WDB will work on the Tk 2.36 billion sub-project to renovate and repair the dam, irrigation, and the river and coastal embankments.
The other agencies working in the sub-projects are—the Disaster Management Bureau, the Food and Agricultural Organisation (FAO), the Department of Agricultural Extension (DAE), the Department of Fisheries (DOF), the Department of Livestock Services (DLS), and the Planning Commission.
Planning secretary Manzur Hossain told bdnews24.com that the government was stressing on escalating local people's ability to tackle future disasters.
NEW AILA PROJECTS
The government has taken up a Tk 3.15 billion project to build and rebuild a 530-kilometre dam and reinstall the infrastructures in the 20 Aila-hit upazilas.
Twenty Aila-hit upazilas are—Dumuria, Dighalia, Dakop, Batiaghata, Paikgachha and Sadar of Khulna, Debhata, Ashashuni, Kaliganj, Shyamnagar, Tala, Kayra and Sadar of Satkhira and Morhelganj, Sharankhola, Rampal, Fakirhat, Mollarhat, Chitalmari, Rupsa, Kachua and Sadar of Bagerhat.
These projects are also expected to be concluded by June, 2013.
Planning minister A K Khandker said on Oct 26 this year that the rehabilitation project in the affected areas had been taken up aimed at reducing damages from any future disasters.
PCMU director Abdur Rauf said a proposal to set up a Disaster Management Response Fund, to combat any sudden disaster, will soon be sent to the government.