Salda 3rd well to yield gas mid-Dec
The gas well is expected to produce 25 million CFT gas every day, reports Aminur Rahman Rasel
bdnews24.com News Service
bdnews24.com
Published :
21 Nov 2011, 02:49 PM
Updated :
10 Aug 2022, 05:50 PM
Aminur Rahman Rasel
bdnews24.com correspondent
Dhaka, Nov 21 (bdnews24.com) – A Salda gas well, which Bapex started digging recently, will produce 25 million cubic feet (CFT) gas every day from mid-December, authorities have said.
Mohammad Shahabuddin, director of the Salda-Fenchuganj Gas Field Development Project, told bdnews24.com on Monday, "Media reported that lifting of gas from the third well of Salda gas field will begin this month, but practically speaking, the development work of the well may lead into the second week of December."
"Once the development work is over, around 25 million CFT gas can be supplied every day using pipelines," Shahabuddin added.
Meanwhile, people of Kasba upzila in Brahmanbaria have started demonstrations to press for fulfillment their demand of gas supply to their area.
The state-run exploration agency Bapex (Bangladesh Petroleum Exploration and Production Company Ltd) began digging the well in Kasba in July.
Chairman of Petrobangla, the parent organisation of Bapex, Hossain Mansur visited the Salda gas field recently. After the visit, Mansur said the gas from Salda will be supplied to Chittagong.
Locals observed a three-hour human chain programme, starting 11 am on Sunday, in Kasba under the aegis of Gas Connection Implementation Committee to protest the Petrobangla chairman's announcement and demanded immediate connection in the area.
"Strong agitation will be held if gas connection is not given to Kasba," Kasba upazila chairman and also convenor of the Gas Connection Implementation Committee Ruhul Amin Bakul told bdnews24.com.
He also reiterated their demanded of gas connection in the area.
With the Salda well, the number of gas producing wells in the country becomes 80. At present, around 6 million CFT gas is being lifted every day from two other wells in Salda.
There are 24 gas fields in the country, of which 17 are in use.
Mohammad Shahabuddin said the digging of a 4th well in Sylhet's Fenchuganj gas field was underway. He added that a drilling steam test (DST) will be conducted by the end of November.
Bapex managing director Mortuza Ahmad Faruque said it would be possible to lift 20 million CFT gas every day from Semutang gas field of Manikchharhi upazila in Khagrachharhi.
The first four wells were drilled here in 1969-70 by the then Oil and Gas Development Company Limited of Pakistan, but were abandoned later.
The work-over project in the field, costing an estimated Tk 650 million, was approved on May 22, 2008 by Executive Committee of National Economic Council.
State-run exploration agency, Bapex, had successfully lifted gas from the fifth well from Semutang field and the Karnaphuli Gas Distribution Company Limited is currently executing the pipeline project.
Faruque said the gas from the field's fifth well, having a recoverable gas reserve of about 150 billion CFT, a small-size field, could be distributed to Chittagong.
The net amount of gas lifted everyday from Salda, Fenchuganj and Semutang gas fields will rise to 100 million CFT within January once extraction in Semutang begins.