Rental Power plants A move reversed
In a reversed move, the power division will now go ahead with its controversial rental power plants proposal despite its estimate that the move will cause a financial loss worth Tk 79.20 billion in 15 years.
bdnews24.com News Service
bdnews24.com
Published :
03 Sep 2006, 06:00 PM
Updated :
17 Aug 2022, 06:37 PM
Dhaka, Sept 4 (BDNEWS) – In a reversed move, the power division will now go ahead with its controversial rental power plants proposal despite its estimate that the move will cause a financial loss worth Tk 79.20 billion in 15 years.
State minister for power M Anwarul Kabir Talukder Monday told BDNEWS that though the issue of rental power plant was not the ultimate solution, it might be a stop gap arrangement as this gap should be filled immediately.
Earlier, he had planned to brief the Prime Minister on the possible effects of installation of these rental power plants from the government exchequer.
The Bangladesh Power Development Board (BPDB) is the sole purchasing power, he said adding that the division would merely calculate gaps as well as loss and profit from the project implementation.
The proposals along with calculations would be sent to the Cabinet Committee on Purchase shortly for its wisdom approval.
Power division sources said the government might count a loss of over Tk 5.0 billion annually to generate only 160 mega-watt (MW) of electricity from five rental power plants as the government would have to purchase electricity from rental power units at higher rates and sell it to clients at subsidised rates.
The government purchase committee had approved five proposals for installation of rental power plants including Shahjibazar 80 MW, Kumargaon 20 MW, Bogra 20 MW, Katakhali 20 MW and Thakurgaon 20 MW by the private sector, sources added.
The nagging electricity crisis across the country pushed the government, last year, to approve a policy to install eight barge-mounted or skid-mounted rental power plants across the country.
The power division had felt that the state-owned power entities might face huge financial drawbacks if the government allowed installing the power plants.
Generation of a mere 160 MW of electricity would not contribute much to improve the power supply situation, said power division officials.
According to the tender documents of rental power providers the state-owned BPDB will have to purchase electricity between Tk 2.62 and Tk 3.01 per kilowatt-hour.
But the selling price of the BPDB's electricity to the Dhaka Electric Supply Authority (DESA) is Tk 1.89 per kilowatt-hour, to the Rural Electrification Board (REB) Tk 1.84, to the Dhaka Electric Supply Company (DESCO) Tk 1.94 and to the West Zone Power Distribution Company Tk 1.94.
It would take at least six months to install rental power plants after the final approval of the government.
The minister, however, said that the division was eagerly working to ensure captive power before the end of the government tenure.
He earlier said that installation of new power plants instead of purchasing rental power at higher prices would be more viable.
Talukder had once pointed out the conditions set by the bidding companies of the rental power projects and said that they were not viable considering the country's economy.
Power sector sources said that the BPDB was currently reeling in a financial crisis due to the non-payment of outstanding power bills worth around Tk 6.0 billion by the independent power plants (IPPs).
BDNEWS/1835 hrs