Published : 25 Nov 2013, 05:59 PM
Updated : 09 Aug 2022, 11:21 AM
The property-development venture had been taken up at Borhkaw and Parabarta Moujas in Gazipur's Kaliganj Upazila.
A five-member bench, headed by Chief Justice Md Muzammel Hossain, passed on Monday the order on a writ petition filed against a Chamber Justice's order.
The order also says the bench will hear the petition within three months.
"The Appellate Division has ordered a status quo on the project, halting all the property development and handover there," said, Liton, speaking to bdnews24.com, after the order.
Assisted by Md Iqbal Kabir Liton, Fida M Kamal argued for the BELA, while Md Motahar Hossain Saju represented RAJUK.
A High Court bench had on Aug 1 stopped the project work in response to a writ petition filed by seven non-government organisations.
The stoppage order was later revoked on Aug 20, prompting the Bangladesh Environment Lawyers Associated to file a writ petition at the Appellate Division that produced Monday's order.
The High Court had, in its original writ order, wanted to know why the new project should not be declared illegal.
The court had also wanted to know why an order to protect the area's forest, farmland, water bodies and the overall milieu.
The Housing and Public Works Secretary, Environment Secretary, Directorate of Environment and seven others had been asked to respond to the rulings within four weeks.
BELA, Ain O Salish Kendra, ALRD, Bangladesh Paribesh Andolon, Save the Environment Movement, IAD and Nijera Kori had jointly filed the writ petition.
According to the writ petition, no environment clearance had been taken for the Purbachal Project.
The petition also stated that no permission had been taken for earth-filling and structural change. Yet, RAJUK has been filling up 1,600 acres of land in this area since 2010.
Forests and water bodies reportedly cover 46 percent of this area.