Project to cut crude transport time okayed
The government has approved a project that would cut time required to transport crude from containers to the Eastern Refineries down to 48 hours at most from at least 11 days.
bdnews24.com News Service
bdnews24.com
Published :
11 May 2010, 01:21 PM
Updated :
11 Aug 2022, 11:42 AM
Dhaka, May 11 (bdnews24.com)—The government has approved a project that would cut time required to transport crude from containers to the Eastern Refineries down to 48 hours at most from at least 11 days.
The Single Point Mooring project in deep sea near Kutubdia will save both time and wastage as this would virtually eliminate the usage of lighterage vessels and lorries for transporting crude and oil from containers ships to the Eastern Refineries in Chittagong.
The project was approved at a meeting of the Executive Committee of the National Economic Council headed by prime minister Sheikh Hasina on Tuesday.
Planning secretary Mohammed Habib Ullah Majumder disclosed the information to reporters after the meeting.
He said, "At present, lighterage vessels carry oil offloaded from ships in the deep sea to the shore. Then oil is transported to the Eastern Refinery by trucks. The entire process needs 11 to 15 days and a good quantity of oil is also wasted in this process."
The Single Point Mooring project would supply oil directly to the refinery that would reduce the time to only 48 hours, he added.
Majumder said that a 77 km-long and 36-inch wide pipeline would be set up by June 2012.
The ECNEC meeting approved four other projects.
The projects are a Tk 58 crore project to develop tourism infrastructure in South Asia, Tk 141 crore project to set up Sheikh Fazilatunnesa Mujib Eye Hospital and Training Institute in Gopalganj, Tk 64 crore project to set up Bangabandhu Sheikh Mujib Safari Park in Gazipur and Tk 33 crore project to construct by-lane on the Sayedpur-Enayetpur link road
bdnews24.com/rb/adk/ta/bd/1909h