Port city suffers from serious power shortage
The port city Chittagong and its surrounding districts were suffering from serious power shortage as both units of Rauzan power stations went down Wednesday afternoon.
bdnews24.com News Service
bdnews24.com
Published :
10 May 2005, 06:00 PM
Updated :
17 Aug 2022, 08:38 PM
Chittagong, May 11 (BDNEWS) – The port city Chittagong and its surrounding districts were suffering from serious power shortage as both units of Rauzan power stations went down Wednesday afternoon.
Officials at Power Development Board (PDB) said the units each 210-megawatt capacity became inoperative as an insulator at the 230-kv substation beside the power plant broke down at about 3pm.
"The first unit does not have any hot starter. So, it will take 72 hours to resume generation. The second unit is expected to be pressed into operation later this night," said an official at PDB head office in Dhaka.
He informed that the average demand in Chittagong is 450-megawatt while the region generates 650-megawatt with the generation from Rauzan, Kaptai and Shikalbaha.
The official admitted load-shedding in Chittagong region as the overall generation in the country was lower than the demand Wednesday.
City dwellers complained serious sufferings due to non-stop load-shedding in many areas in this hot and humid weather.
BDNEWS/2040 hrs