Padma bridge not getting costlier: Quader

The expenses for building the Padma Multipurpose Bridge will not go up despite a long delay in starting the construction, Communications Minister Obaidul Quader has said.

Staff Correspondent

bdnews24.com

Published : 13 Feb 2014, 09:12 PM

Updated : 08 Aug 2022, 06:29 PM

The $2.91 billion project was supposed to be co-funded by the World Bank (WB), JICA, ADB and IDB. But it will still cost the same following the government’s decision to build the bridge on its own, he said on Thursday.

Bangladesh’s biggest ever infrastructural project ran into troubled waters after the WB, the lead financer, raised the stink of ‘corruption’ and told the government it would pull out of the project. The other financiers also withdrew.

The government, however, buoyed by the rising foreign exchange reserves, decided to fund the project from its own resources.

Speaking to reporters, Quader sought to dispel doubts that the construction cost would surge. “We have not thought about increasing the spending.”

The government earlier had said there would not be any change to the original plan of the six-kilometre-long bridge which will have both roads and railway tracks.

But the cost for river training may rise if it took more time due to changes in the tide of Padma River, the Communications Minister said.

He said five firms have already showed interest in the river training project. “We want to begin the bridge’s construction along with river training this year.”

At least 21 southern districts will be connected directly with capital Dhaka if the bridge is built, which will help the economy grow by an additional 1.2 percent, the government said.

Quader was speaking to journalists after a meeting with the Ambassador of the United Arab Emirates to Dhaka Saeed Bin Hajar Al-Shehi at the Secretariat.

About the meeting, he said the Gulf state had expressed interest in funding the public-private partnership (PPP) projects in Bangladesh’s communications sector.

“He [the ambassador] has been given a list of some PPP projects. From that, they will select the suitable projects for investment.”

The minister said he would also visit the UAE to reach an agreement on the issue.