Published : 20 Feb 2013, 05:59 PM
Updated : 09 Aug 2022, 10:16 AM
Economic Relations Division (ERD) Secretary Abul Kalam Azad and JICA Chief Representative Takao Toda signed four agreements, including one for appointing a consultant to the project, at Ruposhi Bangla Hotel in the capital.
Finance Minister Abul Maal Abdul Muhith, Communications Minister Obaidul Quader, the Prime Minister’s Energy Affairs Advisor Tawfiq-e-Elahi Chowdhury and Japan Ambassador in Dhaka Shiro Sadoshima were present.
As per the agreements, JICA will give Tk 9.24 billion for metro rail project, Tk 16.53 billion for National Power Transmission Network Development Project and Tk 36.61 billion for Bheramara Combined Cycle Power Plant Development Project.
Bangladesh will have to pay 0.01 percent interest for the loan, which is payable in 40 years, including 10 years’ grace period.
Japan will give Tk 720 million as grant aid for groundwater investigation and development of deep ground water source in the urban and rural areas.
Muhith said Japan provides more financial aid to Bangladesh than does any other country and expressed his gratitude as it came forward to set up the first metro rail system in the country.
Of the total cost of Tk 220 billion, JICA, the agency that coordinates development assistance on behalf of the Government of Japan, will provide Tk 165.95 billion, while the Bangladesh Government will take care of the remaining Tk 53.90 billion.
The 20.1-kilometer-long Mass Rapid Transit (MRT) Line-6 will run from Uttara Third Phase and pass through Pallabi, the west side of Rokeya Square and Farmgate, Hotel Sonargaon, Ruposhi Bangla, TSC of Dhaka University, Doel Intersection, Topkhana Road and Bangladesh Bank.
Later, the route will be extended up to Sayedabad from Bangladesh Bank through Atish Dipankar Road
A survey was conducted during the caretaker government regime to construct the metro rail or elevated expressway across the capital, which got momentum after the Hasina government took office in January 2009.
But the project got stuck after Bangladesh Air Force (BAF) raised objections to the first design of the proposed metro rail route through Bijoy Sarani stating that its height would hinder air traffic at Tejgaon.
JICA, the main funding agency of the project, then expressed its dissatisfaction over the delay in the project.
The Executive Committee of the National Economic Council (ECNEC), the country’s top economic policymaking body, on Dec 18 approved the overland metro rail service project - Mass Rapid Transit (MRT) Line-6 to ease the city's cluttered traffic.
The project will be implemented in three phases by 2022.
After the government revised the design of the overland metro project by excluding Bijoy Sarani from the original design, the JICA agreed to provide the necessary fund at a meeting with Muhith on Dec 2 last year.
The government said that once the 'Dhaka Mass Rapid Transit Development Project' was implemented, some 60,000 commuters would be able to travel every hour.
According to the Planning Division, the rail tracks would be laid in three phases. The Pallabi-Sonargaon Hotel route (11 kilometres) would be completed by 2019 and the Sonargaon-Bangladesh Bank route (4.4 kilometres) by 2020. The remaining Uttara-Pallabi route (4.7 kilometres) was expected to be completed by 2022.
Acquisition of an additional 22 hectares of land from private owners at Uttara Third Phase was necessary for the project as Rajuk declined to provide it. There will be 16 stations and one maintenance depot under the project.
Dhaka Transport Coordination Authority (DTCA) will implement the project under the supervision of the Roads and Highways Division of the Ministry of Communications. DTCA was formed with the aim of modernising the transport system in the capital.