Khilgaon flyover closed to traffic
Authorities have stopped vehicles using the Khilgaon flyover after one of its pillars caved in a week ago Updates
bdnews24.com News Service
bdnews24.com
Published :
09 Sep 2011, 04:24 PM
Updated :
10 Aug 2022, 05:25 PM
Dhaka, Sept 9 (bdnews24.com)—Authorities have stopped vehicles using the Khilgaon flyover after one of its pillars caved in a week ago.
"All modes of vehicles have been barred to ply on the flyover since 8:30pm as a pillar on the western sank some 2 inches," Khilgaon Police Station's office-in-charge Sirajul Islam said on Friday.
Authorities, however, claim that the fault was not that risky.
Assistant sub-inspector Ferdous Alam told bdnews24.com that authorities had barred heavy vehicles since the fault has been identified a week ago in a pillar near the second turn of the flyover adjoining Shahjahanpur.
The 1.9 kilometre-long and 14-metre wide flyover—constructed under the supervision of Local Government Engineering Department (LGED)—opened on Mar 23, 2005.
Designed by local experts, it took Tk 817 million to construct the flyover, the second in Dhaka.
LGED chief engineer M Wahidur Rahman told bdnews24.com, "I'm at the scene now. There had been no structural damage to the flyover. I can see no fractures either, but only a small part of it has been damaged".
He claimed the damaged part was not a 'big threat' for the flyover.
Former vice-chancellor of BRAC University engineer Jamilur Reza Chowdhury, however, observes that it must be viewed as a risk.
"No matter how trivial is the fault necessary steps must be taken at the earliest after identifying reasons behind it," he told bdnews24.com.
An earthquake specialist, Chowdhury stressed looking for faults in the foundation of the site, "otherwise it may have adverse impact".