an agreement on Improvement of Storm Water Drainage System in Dhaka City (Phase II) was signed Monday between the External Resource Division (ERRD) and the JICA Of Japan. M. Emdadul Haque, Deputy secretary to the ERD and Akio Arai, team leader, JICA Basic Design Study Mission, signed the agreement on their respective sides.
bdnews24.com News Service
bdnews24.com
Published :
19 Feb 2006, 06:00 PM
Updated :
17 Aug 2022, 05:51 PM
Dhaka, Feb 20 (BDNEWS)- an agreement on Improvement of Storm Water Drainage System in Dhaka City (Phase II) was signed Monday between the External Resource Division (ERRD) and the JICA Of Japan. M. Emdadul Haque, Deputy secretary to the ERD and Akio Arai, team leader, JICA Basic Design Study Mission, signed the agreement on their respective sides. The project is run on grant aid from the Japanese government.
Team members of the Basic study mission and JICA officials were also present on the occasion, a press release said.
The main objective of this project is to mitigate the adverse effects of water logging due to heavy rains and blocked drainage system in Dhaka city.
The main components of the project include: expansion of Kallyanpur pumping station-cum-sluice gate and canal maintenance and operation equipment. It is expected that that the project, if implemented, will improve the drainage system of Dhaka city.
A seven Member Basic Design Study Team was dispatched to Bangladesh on February 13. The mission's comprised of officials from JICA headquarters, Tokyo and consultant members belonging to CTI Engineering International Co. Ltd, Japan.
The mission visited the project sites of kallyanpur Pumping Station and areas adjacent to Kallyanpur and Segunbagicha canals. Mission members also had extensive meetings with the concerned ministry and DWASA officials.
During their one-month-long visit to Bangladesh, the team will conduct extensive survey of the project area for the basic design report of the project.