Indecision, lack in continuation in project implementation responsible for power crisis
Indecision and lack in implementation of projects are responsible for serious power crisis at the beginning of the summer this year, experts said.
bdnews24.com News Service
bdnews24.com
Published :
17 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:20 PM
Dhaka, March 18 (BDNEWS) – Indecision and lack in implementation of projects are responsible for serious power crisis at the beginning of the summer this year, experts said.
The country experienced highest 770-megawatt load shedding in a day in the current month.
The experts apprehended a daily shortage of 1,200-1,500 MW if the government's bid to suspend operation of industries and shopping malls in the peak hours is not properly implemented.
The business community already rejected the government's load management plan calling it absurd.
A bid of holding responsibility each other by Power and Energy Divisions has also become visible. State Minister for Power Iqbal Hassan Mahmood in a meeting of parliamentary standing committee blamed inadequate supply of gas for the crisis.
On the other hand, Petrobangla and its companies Titas and Bakhrabad said the Power Development Board (PDB) needs 700 million cubic feet of gas per day (MMCFD) for electricity generation.
"Currently we are supplying 600-650 MMCFD. So, it is not acceptable that 600-700 MW less electricity is being generated for shortage of 50 MMCFD gas," said a Petrobangla official.
The state-run oil-gas and mineral corporation, however, admits that generation in Ghorashal plant might be affected due to gas problem.
"But there will be no problem at all when 70 MMCFD gas will be added to the national grid from Unocal's Moulvibazar field from April 5," said the official.
A top official of the PDB said blaming gas supply is a lame excuse.
According to him, PDB's installed capacity is 5,000 MW, but highest 4,100 MW generation is possible.
"Machinery of 50 percent of total installed capacity is 20-years-old. So those are not dependable. Also, generation of 400 MW is now suspended due to maintenance. PDB's present highest generation in no way is more that 3,750 MW."
On the other hand, present demand in the peak hours is 4,200-4,300 MW. "Several power plants get non-operative during the peak hours. Present crisis is worse than 1998 crisis," said the PDB official.
However, following the 1998 crisis the government took emergency steps and installed three barge-mounted plants, three 10-MW stations and two independent power producers (IPPs) of 450 MW and 360 MW capacity were installed.
"With the involvement of the IPPs, which now supply 1,200 MW, the situation was more or less acceptable level till last year," said an expert.
He said soon after the coalition government took over in 2001, it cancelled all the power projects initiated during the past government in excuse of corruption.
But in last three-and-half-years only Siddirganj 210-MW, initiated nine years back, and Tongi 100-MW peaking plant came to generation stage.
The country needs annual addition of 600 MW.
The expert said due to inconsistent policy and lack of initiative, a number of power projects did not see the light.
Those included Sirajganj 450 MW, Sylhet 150 MW, DNPP 450 MW, Shambhuganj 70 MW, Fenchuganj 90 MW, Haripur 109 MW, Meghnaghat (2nd phase) 450 MW, Siddirganj (2nd phase) 210 MW and 10-30 small power units.
State Minister for Power Iqbal Hassan Mahmood blamed red tapism for non-implementation of the projects.
But the experts said responsibility goes to inconsistent policy of the government and tug of war among different government bodies.
They apprehended more crisis in future as the present government will not be able to implement any new project during its rest one-and-half-year tenure.
BDNEWS/2008 hrs