IDB to finance 450-MW DNPP project
Islamic Development Bank (IDB) will finance Dhaka North Power Plant (DNPP) project of Rural Power Company Limited (RPCL), which earlier had become uncertain for objection raised by several donors.
bdnews24.com News Service
bdnews24.com
Published :
04 Mar 2005, 06:00 PM
Updated :
17 Aug 2022, 08:16 PM
Dhaka, March 5 (BDNEWS) – Islamic Development Bank (IDB) will finance Dhaka North Power Plant (DNPP) project of Rural Power Company Limited (RPCL), which earlier had become uncertain for objection raised by several donors.
Two Palli Bidyut Samities (PBSs) will also finance the 450 MW project as an equity partners.
German funding agency KfW primarily expressed its interest to invest in the project, but complexities arose following objection from the Asian Development Bank (ADB) and USAID. KfW expressed its unwillingness to finance DNPP raising allegation of irregularities in the Shambhuganj project of RPCL.
IDB will provide US$ 60 million in the project. On the other hand, KfW was scheduled to finance Euro 35 million while initiator of the project, the PBSs on behalf of RPCL, was scheduled to give Tk 300 crore.
Recently, a delegation from ADB met State Minister for Power Iqbal Hasan Mahmud and expressed their interest to finance for setting up a 450 MW power station.
When a asked if ADB would finance the DNPP project, State Minister for Power told BDNEWS that IDB is going to finance it.
On the other hand, he said the government has the proposal from ADB and a decision in this regard would be taken after consultation with Finance and Planning Minister M Saifur Rahman when he will be back home from abroad.
A power station was first built in the 90s as IPP (Independent Power Producer) in Mymensingh, which was not in the public sector. RPCL installed it following the model of ADB while construction works for its third unit is now going on.
But when RPCL, following the model of PBS, took the initiative to set up a 450 MW new power station at Konabari adjacent to Dhaka, the ADB raised its objection against the move. It said the private sector is able to make IPP successfully, so RPCL should not go for investment in IPP.
On the other hand, USAID that was the pioneer for REB model also opposed the DNPP. They informed the government that the PBS should not invest in the generation side. Rather, they should go for investment in the distribution.
Amidst such a row, its implementation was hanging on the balance. In the mean time, RPCL has bought a place at Konabari for the project and completed its development works.
As IDB agreed to invest in the DNPP, it got a new lease of life.
In this regard, the State Minister for Power said, "I do not see any barrier to implement the DNPP. Its implementation would be ensured at a proper time."
At present, PDB is purchasing power from all IPPs, including from Shambhuganj plant, and supplying to DESA and REB at a government-fixed price. But the uniqueness of DNPP project is that the agreement to purchase power from the power station would be between RPCL and, Dhaka Palli Biddyut Samity-1 and Narsingdi Palli Biddyut Samity-1.
BDNEWS 1839 hrs