Hatirjheel building fate left to 'goodwill'
Loath to put pressure on BGMEA to move off contentious building, the govt waits for good sense to prevail
bdnews24.com News Service
bdnews24.com
Published :
04 Jan 2012, 04:32 PM
Updated :
09 Aug 2022, 03:15 PM
Dhaka, Jan 4 (bdnews24.com) – The state minister for housing has expressed the government's reluctance to press BGMEA authorities to remove its building from inside the Hatirjheel project.
"The government will instead wait for goodwill of the BGMEA authorities," Abdul Mannan told reporters while visiting the Hatirjheel project in the capital on Wednesday.
He said the government would act as per the High Court's directions in this regard.
"But we won't apply force in any way," he stressed. "I believe they (BGMEA) will be good enough to leave the place in the interest of the project."
On Apr 3 last year, the High Court had ordered knocking down the building constructed by Bangladesh Readymade Garment Manufacturers and Exporters Association (BGMEA) inside Hatirjheel project, violating the waterbody protection law.
Two days later, the Appellate Division had stayed the High Court order.
According to BGMEA, they bought the land for Tk 51.7 million from Export Promotion Bureau and completed the construction work in 2006.
BGMEA is alleged to have constructed the building without approval from the Rajdhani Unnayan Kartripakkha (Capital Development Authority) and in violation of the city development and building construction law.
HATIRJHEEL PROJECT BY THIS DEC
Before Wednesday's visit, Mannan informed the media about progress of the project at Karwanbazar camp of Bangladesh Army, the project implementation agency.
He said the project works would be completed by December this year. "Land acquisition and excavation are nearing completion and 70 percent work on the four bridges and overpass has already completed," he said.
Mannan said people around Hatirjheel at present have to endure excessive carbon and stink. Living standard in the locality would improve once the project is implemented, he said.
"There will be service roads and walkways by the lake (post-implementation)," the state minister added.
Asked about the delay in project implementation, Mannan said 72 cases were filed over the project, which impeded a smooth flow of work. "The project works are being done with settlement of the cases," he said.
The Hatirjheel project is being implemented at a cost of Tk 19.71 billion.