November 21, 2026

Haor floods: Water Development officials ‘admit to irregularities’

Officials of the Water Development Board have admitted to massive irregularities in projects for building and repairing embankments in wetlands at Sunamganj.

Staff Correspondent

bdnews24.com

Published : 04 May 2017, 09:19 PM

Updated : 05 Aug 2022, 07:19 PM

The questioning of top BWDB officials has revealed “huge negligence” on part of the agency in charge of supervising the projects, Anti-Corruption Commission’s Director General Muhammad Munir Chowdhury said on Thursday.

“They have failed to properly implement these projects. Everyone starting from its director general said they couldn’t do measurements for repairing dams because they were under water.”

Two projects for building and repairing 37 submerged dams, worth Tk 650 million, were taken up in 2016, according to a report by the National Security Intelligence, which investigated corruption in the projects.

“Two contractors did not work after securing the dam projects. But they were still able to secure more project works,” said Chowdhury. 

The ACC summoned four officials of the water resource ministry, including its joint secretary, over irregularities on Thursday.

They are Joint Secretary Md Khalilur Rahman, Bangladesh Water Development Board Director General Jahangir Kabir, Additional Director General Abdul Hye and Supervising Engineer Harun Ur Rashid.

An ACC team led by Muhammad Munir Chowdhury questioned them from 12:30m to 2:45pm.

“The Water Development Board has terribly failed to implement and monitor the projects. They have confessed to that,” he told reporters after the interrogation.

The BWDB has also ignored the ministry’s order to take departmental action by assigning an engineer as Officer on Special Duty, he said.

He did not make any comment when asked about the statements of the director general.

Last year in April, the ACC wrote to the water resources ministry asking about the damage to crops due to the caving of dams in Sunamganj's Haor areas.

The ministry filed its report to the ACC in February this year, upon which the BWDB officers were summoned.

The wetlands got submerged early April due to heavy downpour. The projects were due to be completed by Mar 31.

The floods have damaged 219,840 hectares of crop fields in Sunamganj and adjoining six districts, leaving 850,088 families to count massive losses.

Rivers overflew and submerged crops as rickety and incomplete dams caved in during the flash floods.

Three engineers of Bangladesh Water Development Board have been suspended following the charges of corruption in building the dams.