Dhaka, Sep 8 (bdnews24.com) — The government has approved installation of four power plants, one of which will be coal-fired.
Finance minister A M A Muhith on Thursday told reporters after a meeting of the cabinet committee on purchase that the coal-fired plant would come into operation in a little less than four years.
"The other three running on furnace oil will begin production within a year."
Cabinet Division joint secretary Nurul Karim told journalists, "The 300-650MW coal-based power plant will be established in Munshiganj's Mawa area. Long King-Orion Joint Venture Company will set up the plant. The government will purchase power from them at Tk 4.09 per unit."
A 108-MW furnace oil-based plant will be set up in Keraniganj's Bosila area by CLC Power and Engineering Ltd. Per unit power from the plant will cost Tk 6.92.
Two 52-MW power plants will be set up in Comilla's Homna area and Munshiganj's Katpotti area. The plant in Comilla will be set up by a joint venture between Union Consultants and Venture Energy Resources Ltd while the plant in Munshiganj will be set up by People's Energy and Venture Energy Resources Ltd. The government will purchase power from both the plants at Tk 6.96 per unit.
Nurul Karim said the committee also proposed appointing contractors for dredging a 14-kilometre-stretch from Jamuna's Sirajganj hard-point to upstream of Bangabandhu Bridge under the Capital Dredging of River System in Bangladesh project. China Harbour Engineering Company was given the project worth Tk 4.63 billion.
The joint secretary added that the committee also approved procurement proposal of 11 metre-gauge diesel rail engines at a cost of Tk 2.9 billion under the Dhaka-Chittagong Railway Development Project. Marubeni Corporation will implement the procurement.