Glitches grind Barapukuria plant down
Just four years after the launch of the country's first coal-fired 250MW power plant at Barapukuria, frequent mechanical troubles are severely hampering its production, Morshedur Rahman reports from Dinajpur.
bdnews24.com News Service
bdnews24.com
Published :
24 Sep 2010, 02:20 PM
Updated :
24 Apr 2022, 05:40 PM
Morshedur Rahman
bdnews24.com Dinajpur correspondent
Dinajpur, Sep 24 (bdnews24.com) — Just four years after the launch of the country's first coal-fired 250MW power plant at Barapukuria, frequent mechanical troubles are severely hampering its production.
The problem has become so acute that the two units (125MW each) cannot be run simultaneously. Since Sep 20, the second unit has been shut due to mechanical problem and the first unit can only produce 60MW a day.
Biswanath Halder, chief engineer of the plant, on Friday told bdnews24.com that the second unit could resume production within 10 days.
"We're undertaking renovation work in both the units next month to ensure uninterrupted long-term production," Halder added.
Launched in 2006, the Barapukuria plant had been producing 220MW electricity for about three years. But production started to go down since 2009 and most of the times only one unit could be kept operational at a time because of repeated mechanical problems.
Several officials of the plant, asking not to be named, said low quality machinery was used in the plant supplied by its Chinese contractor, which is causing this trouble.
Another significant reason behind drop in generation is the use of low-quality Indian coal, which the authorities were forced to import when coal supply from the adjacent mine was halted for around three months in 2007.
According to officials, the first unit was shut down on Sep 13 and the second unit on the very next day.
Later on Sep 16, the first unit resumed production and the second one on the following day. Total generation stood at 125MW to 140MW until the second unit was shut on Sep 20.
The plant was implemented by Bangladesh Power Development Board at a cost of Tk 1,660 crore and constructed with suppliers' credit on 300 acres of land.