Published : 08 Sep 2013, 12:05 AM
Updated : 09 Aug 2022, 11:05 AM
Ashuganj power plant’s Chief Engineer Abu Bakar Siddiqui said the problems occurred around 7pm on Saturday.
He, however, said it would be possible to fix the problem in four of the affected plants by night.
Officials there say around 800 megawatts of power are fed into the national grid from the seven units.
Parts of Brahmanbaria, Mymensingh and Sylhet districts are facing blackouts due to the problem.