November 20, 2026

Developer ignored defect in killer lift

A worker says the lift that made a disastrous free-fall at a construction site, killing four workers on Thursday, was flawed but authorities had no time to fix it.

bdnews24.com News Service

bdnews24.com

Published : 22 Jul 2011, 12:17 PM

Updated : 10 Aug 2022, 05:09 PM

Dhaka, July 22 (bdnews24.com) —The lift at the Kakrail construction site where four workers died on Thursday was troubled, the site's head bricklayer has said. "The lift was not flawless. Authorities did not pay heed to repeated requests from workers to fix it," Asgar Ali alleged in the case filed on Friday. The rope of the lift was once snapped earlier too, he added. But no casualties were reported as none had been on it, he said. Comment from the developer company was not immediately available to confirm Ali's allegations. The accident took place around 7pm at Iris Nurjahan Tower and workers 'Jahidul', 24, Abdur Rahman, 22, 'Rubel', 22, and 'Delwar', 20, died after they were taken to Dhaka Medical College and Hospital. A case was filed around 12:30am with the Ramna Police Station, for neglecting duties, against five including owner of the developer Building for Future Limited Tanvirul Huq Probal, officer-in-charge Rafiqul Islam told bdnews24.com. The other accused are site manager Tanvirul Hassan, project manager Gazibur Rahman, general manager Mohammad Aslam and tiles contractor Mohammad Hannan. Asgar on Thursday told bdnews24.com the boys had been working at the site for about one-and-a-half months. "They were going to the 13th floor carrying tiles when the accident happened," he said. bdnews24.com/kt/sh/pks/jr/1811h
Related Stories