Dhaka, Jan 29 (bdnews24.com)—The government on Sunday signed an agreement with India to set up the biggest power station ever, with production capacity of 1320 megawatt (MW).
Bangladesh Power Development Board (PDB) struck the deal with India's public sector National Thermal Power Company (NTPC). This is the 50th agreement signed by the Awami League-led government to set up power stations in Bangladesh.
PDB chairman A S M Alamgir Kabir and NTPC chairman Arup Roy Chowdhury signed the agreement.
The PDB chief said the power plant will be set up at Bagerhat's Rampal and Bangladesh and India will have equal partnership in production. "We hope to supply electricity to the national grid by 2016," he said.
The government signed a memorandum with NTPC on Aug 30 last year and had acquired 1,834 acres of land near the Mangla port for the project.
There are two units of coal-based power stations in Barapukuria with a total production capacity of 2,500 MW.
At present, Bangladesh produces power from five types of fuels: gas is used for 82 percent of power generated, furnace oil for 5 percent, diesel for 7 percent, while water and coal-based power make up for the remaining 3 percent power generated.
The country's present power production is slightly more than 5,000 MW against a daily demand of 7,000 MW.
The government has undertaken plans to step up power production to 15,000 MW by 2016.
To realise the plan, the government so far has signed agreements to set up 50 power stations. Among these, 17 are quick rental-based stations, three are rental based, 11 are independent power producers, while the other 19 are public.