Chittagong, Sept 21 (bdnews24.com)- Chittagong is witnessing the worst ever load-shedding this week causing a sharp decline in industrial production as well as immense sufferings to the city-dwellers.
Power situation has not improved even a little as not a single megawatt is added because no new power plant has been set up in Chittagong over the past nine years. A drastic increase in demand has, however, set in during the period.
Production in hundreds of export oriented industries in the city has dropped to the lowest level resulting in a loss of nearly Tk ten crore on an average per day, a highly placed source said.
Water supply has also dropped drastically due to the power crisis while other power-based activities are being stalled adding to the miseries of the city residents.
The power crisis deepened in the city as a major portion of the electricity generated in Chittagong is being diverted to the national grid without meeting the local demand, sources said.
According to PDB sources the port city is facing a 200 to 240 MW load-shedding per day since this week against the demand for nearly 550 MW everyday.
A total of 443 MW of electricity was generated at four power plants in Chittagong on Wednesday of which 170 MW was supplied to the national grid.
There was load shedding for 16 to 18 hours in areas under Khulshi and Pahartali power substations, the worst hit areas in recent times, on Wednesday.
" We suffer 18 hours of load shedding as power supply does not last for more than an hour a day, and we are unable to keep production level normal even with our reserve power " said Kamaruddin Ahmed, Director of the Fish Preservers Ltd.
located in the city's Baiyazid Bostami area.
He said that shipments of products had been cancelled or deferred due to power crisis resulting in the loss of nearly half a crore taka.
Maksudur Rahman, President of Frozen Food Exporters Association said that it was nearly impossible to maintain the freezing standard of nearly 28 fish processing units in Chittagong, and that the total production in those units had declined to 1.5 tonnes from ten tonnes.
The situation in 264 garments industries in the city is also grim due to continuous load shedding.
While talking to bdnews24 .com BGMEA President S M Fazlul Haq demanded supply of power for five to ten hours everyday on a rationing system to keep production uninterrupted.
Chittagong Chamber President Saifuzzaman Chowdhury said that supply of power to the national grid should be made after meeting the demand of Chittagong.
Meanwhile, Greater Chittagong Development Action Council led by Chairman of the Daily Purbokone Ltd Mohammad Yusuf Chowdhury has issued a 15-day ultimatum to the Chittagong WASA to supply water to the city dwellers without uninterruption and withdraw the surcharge imposed on installation of deep tubewells that had aggravated the water crisis.
At present, Chittagong WASA is only generating 3.5 crore gallons of water against the demand for nearly 11 crore gallons per day.
Raozan Thermal Power Plant (unit –2) with 210 MW power generation capacity was the last unit to be set up in 1997 and went on commercial production on September 20 the same year.
Chittagong has four power stations with a total of 756 MW generation capacity. Two units are at Raojan with a 420 MW capacity, five units at Kaptai hydel project with 220 MW, Shikalbaha with 60 MW and two units of barge mounted plants with 56 MW.
The fourth and fifth units of Kaptai and one barge mounted unit have been closed since long.
Even one of the units of Kaptai has remained shut down for years since the water level of the Kaptai lake dropped.