The country experienced serious power crisis Wednesday with highest generation of 3,400 megawatt against peak-hour demand of 5,200 MW, officials concerned said.
bdnews24.com News Service
bdnews24.com
Published :
02 May 2006, 06:00 PM
Updated :
17 Aug 2022, 06:08 PM
Dhaka, May 3 (BDNEWS) – The country experienced serious power crisis Wednesday with highest generation of 3,400 megawatt against peak-hour demand of 5,200 MW, officials concerned said.
The crisis aggravated as two major plants were generating less than their actual capacity due to maintenance and other technical reasons.
Only 600 MW was available from Ghorashal plant that can generate 950 MW. Ashuganj plant with 724 MW capacity generated only 410 MW.
On the other hand, Raozan could generate 290 MW against 420 MW capacity due to gas problem.
Suspension of generation also included Haripur 100 MW, Karnaphuli (4, 5) 100 MW, Shahjibazar 95 MW and Baghabari 71 MW.
Loadshedding in many areas of the capital was so severe that people got electricity for every alternative hour.
Northern districts and port city of Chittagong were also worst victims of the crisis.