Clean Dhaka master plan uncertain due to irregularities in bidding
Irregularities in the bidding and violation of agreements have irked Japan, the financier of the Tk 360 crore Master Plan Project on Solid Waste Management in Dhaka, leading to uncertainty in its implementation.
bdnews24.com News Service
bdnews24.com
Published :
03 Mar 2006, 06:00 PM
Updated :
17 Aug 2022, 05:54 PM
Sajjadur Rahman
BDNEWS Writer
Dhaka, Mar 4 (BDNEWS) – Irregularities in the bidding and violation of agreements have irked Japan, the financier of the Tk 360 crore Master Plan Project on Solid Waste Management in Dhaka, leading to uncertainty in its implementation.
Visiting high-powered Advisory Team of the Japan International Cooperation Agency (JICA) Saturday expressed their dissatisfaction over the dismal progress in execution of four priority projects under the Clean Dhaka Master Plan, DCC sources told BDNEWS.
Officials of JICA's local office and Japan Bank of International Cooperation (JBIC) also voiced their dismay at the progress in implementation of the scheme.
JICA Study Team for preparation of the master plan, JBIC, Economic Relations Division (ERD) of the Finance Ministry and LGRD and Cooperatives Ministry sought explanations from the Dhaka City Corporation (DCC) for alleged violation of the Public Procurement Regulations (PPR) in appointing consultant for the project, DCC sources said.
"I know there are some problems with the consultant selection process for the Tk 47 crore Landfills Improvement Project in DCC," Akiko Bhushimata, deputy resident representative of JICA in Dhaka, told BDNEWS.
"JICA Study Team has already raised the issue with DCC," she said.
Sources said the JBIC also called the DCC officials concerned at its Dhaka office and sought explanations from them on the irregularities in the bidding for appointment of an international consultant.
Earlier in December, the DCC invited tender from experienced international firms seeking consultancy services for analysing environmental impact and detailed design of the construction of Landfills Improvement Project. Signing of the contract was supposed to be done by February this year for completion of the project by June 2007.
A total of nine proposals from countries, including India, US, UK, Germany and Pakistan were submitted to the Project Director of the Solid Waste Management in Dhaka City. But the DCC rejected all the proposals and tried to award the contract to Bangladesh University of Engineering and Technology (BUET) by violating the PPR.
Following DCC's decision, JICA talked to the professors of BUET and found that they have no experience in this field, JICA Study Team members said.
"The Landfills Improvement Project is the outcome of the master plan preparation with technical and financial support from Government of Japan and non-transparent process of contract award will result in huge financial loss and tarnish the image of the nation as well," Lt. Col. Mir Nazrul Islam, chairman of the Global Environment House, one of the nine bidders, told DCC in a letter circulated to concerned ministries and divisions of both Japan and Bangladesh on February 9, following DCC's rejection of all the proposals illegally.
The DCC also failed to comply with the agreements between the DCC and JICA about staffing the waste management division (WMD), which the JICA Study Team termed 'clear violation' of the agreements.
A JICA study team member told BDNEWS that the WMD was supposed to be staffed with the counterpart personnel who received the technology from the JICA study team, but the DCC recruited most the staff from beyond the counterpart.
The Corporation also removed the project director of the Landfills Improvement Project by violating government directives in this regard, said a DCC official, requesting anonymity.
Now incompetent and inexperienced personnel of DCC are running the WMD, DCC officials said. Although the Superintendent Engineer (SE) of the WMD was responsible for improvement of fuel and cleaner pilferage and vehicles maintenance as per the decisions of the 3rd meeting of the Waste Management Committee (WMC), held on March 7 last year, he failed fully to execute those.
The DCC signed an agreement with JICA, endorsed by both governments, on July 16, 2003 to implement the 10-year-long Tk 1,000 crore (as per the quotations of DCC Mayor) "Clean Dhaka Master Plan Project". Later, the project cost was reduced to only Tk 360 crore due to SE of WMD's failure to identify the project components properly.
BDNEWS/1819 hrs.