He told reporters at the Secretariat on Wednesday, “I hope the prime minister will inaugurate this key highway in the last month of May after it is given the finishing touches.”
The minister’s statement came a day after ECNEC approved extension of the deadline to December, 2016 to upgrade the Dhaka-Chittagong Highway to four lanes, along with an increase in the project cost by 20 percent.
The project cost has increased from the initially approved figure, Tk 21.68 billion, to Tk 38.17 billion, of which Tk 6.27 billion is being pumped in the form of fresh allocation.
The minister dismissed the idea that the cost of the project had gone excessively high.
A kilometre of the Dhaka-Chittagong Highway is costing less than Tk 200 million while the four-lane highway in Joydebpur will cost Tk 400 million a kilometre, he said.
Quader said finishing the layer work on the 121 kilometre stretch of the road, construction of 23 bridges and 241 culverts, and a 31 kilometre bypass realignment had been completed.
When the project first got the ECNEC go-ahead on Dec 26, 2005, it was supposed to be completed by June, 2012. Later, the deadline was reset to December 2014 following two extensions.
PM will open 18 bridges
Quader said Prime Minister Sheikh Hasina will inaugurate 16 bridges on the Sylhet-Sunamganj and Sylhet-Zakiganj highways and two others on Patuakhali-Kuakata road through video conferencing from Ganabhaban on Feb 25.
The minister talked to reporters after a meeting that reviewed the Annual Development Programme.