1,700 MW power shortage this summer likely
The country will experience a shortage of 1,700 megawatt of power every day in the coming summer. The deficiency is estimated to be one third of the total demand. Power Division sources said, though the government had taken a one-year plan to cope with the power crisis, it would not be able to make up for the deficiency of more than 1,700 MW this summer.
bdnews24.com News Service
bdnews24.com
Published :
17 Feb 2007, 12:35 PM
Updated :
17 Aug 2022, 02:27 PM
Ahmed Dipu and Ehsanul Haque
bdnews24.com Administrative Affairs Correspondents
Dhaka, Feb 17 (bdnews24.com)- The country will experience a shortage of 1,700 megawatt of power every day in the coming summer.
The deficiency is estimated to be one third of the total demand.
Power Division sources said, though the government had taken a one-year plan to cope with the power crisis, it would not be able to make up for the deficiency of more than 1,700 MW this summer.
During the time highest supply could be about 3,500 MW against a demand of 5,200 MW.
If the production of power could be retained at the present level and gas supply uninterrupted the residential subscribers of power would not be able to get more than 2,000 MW in the summer.
The rest of the supply would be consumed by factories, steel and re-rolling mills, markets and shops, bill boards and road lights. More than 1,529 MW of electricity is consumed by these sectors.
Against this backdrop, power division secretary AKM Zafarullah Khan told bdnews24.com Saturday that they had started their work as per plan. The electricity to be available after renovation of captive power and rental power plants and power stations would be added to the national grid. Besides, some electricity could be saved through load management. This would help reduce the crisis to some extent.
The power division took up a work plan for next years with the aim of increasing production following a decision of the council of advisers. It mentioned that electricity production could be increased by 958 MW by December, 2007.
However, as per the plan increasing power generation by more than 675 MW is not possible in any way by June next, the power division sources said.
Power division sources also said, the present production capacity of the existing power stations was 2,800 MW. Another 675 MW would be added in June next raising the total power generation to 3,475 MW.
As per the plan of the power division, the sources from where 675 MW of additional power will be available by June next are: 400 MW from the power stations now undergoing overhaul, 180 MW from under-construction power stations, 90 MW from rental power plants and five MW from captive power plants.
Some more electricity could be saved through load management that would contribute to reducing the deficiency.
The government plan mentioned that the installed capacity of all power stations of the country was 5,275 MW. Of the total 97 power units, 29 are more than 20-year old. Their lives have already expired. Production capacity of these old stations has come down to 4,582 MW.
On the other hand, 11 units have remained closed for maintenance and repairing. Taking all these into consideration the power stations are now producing 2,800 MW electricity.
As per the government plan to overcome the power crisis, activities of setting up new power stations would be taken up in 2007. The government plan expressed hope that it would be able to add 3,435 megawatt power to the national grid in the near future.