3 big projects kick off in 2014

Several big projects in the communications sector, held in abeyance for a long time due to political unrest, have finally seen the light along with the Padma Bridge project.

Shamim Ahmed

bdnews24.com

Published : 31 Dec 2014, 04:59 PM

Updated : 19 Oct 2022, 07:48 PM

The 'physical work' on Dhaka's Elevated Highway also started this year, while the tender process for the Metro Rail Mass Transit System is underway.

Padma Bridge

The Awami League had taken the initiative to begin work on the bridge soon after it came to power in 2009 to fulfil its electoral pledge.

The World Bank had promised a loan of $1.2 billion for the $2.9 billion project but the deal ran aground due to allegations of corruption soon after signing the agreement in 2011.

After a series of discussions, it agreed to revive its pledge, but on several conditions.

The deal, however, fell through in January 2013 following differences over an investigation into corruption charges.

Later, the government decided to execute the project with its own funds. Earlier this year, the government inked deals with two Chinese companies for the construction of the bridge and river training.

The construction of the main bridge, in four years, will cost Tk 121.32 billion, while the budget for river training is Tk 87.0781 billion.

Joint Venture of Korea Expressway Corporation will supervise the construction of the bridge, the longest in Bangladesh.

Construction of the 6.15km bridge, which the government says will be completed by 2018, is already underway.

Project Director Mohammad Shafiqul Islam said, "Fourteen percent of the work has been already done. I hope 30 percent of it will be over by next year."

Metro rail


The metro rail project work kicked off after the Cabinet approved in principle a law (Metro Rail Act 2014) related to land acquisition for the metro rail on Apr 28 this year.

In September, Road Transport and Bridges Minister Obaidul Quader announced the metro rail alignments and the 16 stations. The detailed design will be finalised next July, the project director said.

The road transport minister had said that the tender process would begin in December. However, the tenders are yet to be floated.

Preparations are being made for floating eight tenders in six packages next year for the 21km metrorail.

Project Director Md Mofazzal Hossain said the tender would be floated at the beginning of the new year. Construction will get underway, once the process ends.

Of the total cost of Tk 220 billion, JICA, the agency that coordinates development assistance on behalf of the government of Japan, will provide Tk 165.95 billion. The Bangladesh government will take care of the remaining Tk 53.90 billion.

But citizens will have to wait for another four years for a metro rail ride.

The 16 Metrorail stations will be Uttara (North), Uttara (Centre), Uttara (South), Pallabi, IMT, Mirpur 10, Kaziparha, Taltala, Agargaon, Bijoy Sarani, Farmgate, Sonargaon, National Museum, Doel Chattar, Bangabandhu National Stadium and Bangladesh Bank.

Dhaka Elevated Expressway

After missing two deadlines, the road transport minister said the construction of the much-talked-about elevated expressway will start by the end of October.

The 46-km long expressway including the connecting roads will cost around Tk 122 billion.

It will connect the Shahjalal International Airport with Kutubkhali via Mohakhali, Tejgaon and Kamalapur.

According to Project Director Kazi Mohammad Ferdous, about 10 percent of work has been completed.

He hopes that 30 percent of it will be complete by next year.