June 10, 2026
The third unit is expected to return to service by mid-May
The closure of the last unit is due to a boiler burst triggered by stones passing with coal, authorities say
Second and third units remain offline, with third unit expected to restart in nearly two months
Chief engineer says it will take at least a week to resume operations
Boiler pipe leakage shuts down two units supplying 230MW to the national grid