Lack of China funds stalls Padma bridge rail links
Zafar Ahmed, bdnews24.com
Published: 2018-01-09 11:11:44.0 BdST Updated: 2018-01-09 15:03:29.0 BdST
The Padma rail link project seems uncertain as the government has failed to sign a loan agreement with a China bank in time.
A railway ministry letter sent to the Prime Minister’s Office in November 2016 says the rail ink project must be rolled out in January 2017 for launch in 2019 along with the Padma Bridge.
The rail communication must start simultaneously with the launch of the bridge, as per orders from the prime minister, according to the letter.
“The implementation of the project will start once the loan agreement is signed with China by December 16,” it read.
But the Economic Relations Division under the Ministry of Finance is yet to sign the loan agreement with the Export-Import Bank of China thus stalling the project.

“But we are still hopeful that it may be signed within next few weeks.”
The delay has been caused because the Chinese government wants to go by its law, he added.
A senior ERD official told bdnews24.com that the Chinese government told Bangladesh at the eleventh hour that permission from the China’s state councillor was mandatory for the deal to be signed.
The Tk 350 billion project is for building 172km railway tracks over the Padma bridge from Dhaka to Jessore.
It is among the 27 deals including 12 loan and mutual agreements that Bangladesh and China signed during Chinese President Xi Jinping’s Dhaka visit in 2016.
China is due to provide Tk 250 billion in loans while Tk 100 billion will come from the Bangladesh government.
A seven-strong delegation led by State Minister for Finance and Planning MA Mannan will visit China sometime between Jan 21 and Jan 23 following the green light from Prime Minister Sheikh Hasina, said an ERD official.
“The visit is yet to be finalised although a proposal has been made,” ERD Secretary Kazi Shofiqul Azam told bdnews24.com.
Kazi Shofiqul Azam, Md Zahidul Haque, and Railway Secretary Md Mofazzel Hossain are among the delegation members.
The Padma bridge project is due to be complete in 2020, as per latest adjustments that extended the deadline by two years.
On Dec 27, the PMO issued a letter to the ERD asking it to convey the matter to Chinese authorities and sign the loan agreement with no delay.
More stories
WARNING:
Any unauthorised use or reproduction of bdnews24.com content for commercial purposes is strictly prohibited and constitutes copyright infringement liable to legal action.
- In London, Hasina emphasises connectivity for stability in Asia
- Hasina describes Bangladesh’s journey towards 'self-reliance' to London audience
- Islami Bank Chairman Arastoo Khan resigns
- Work in full swing to make metro rail project ‘visible’ by June
- China to set up Hainan free trade zone by 2020, port by 2025: Xinhua
- Muhith ‘not sure’ what he said on taxing private universities as govt distances itself
- World Bank to lend Bangladesh $515 million for two projects
- Where is the source of growth? WB asks casting doubt on Bangladesh's GDP projection
- Government savings certificates borrowing exceeded target in first eight months in FY18
- Boro rice: Tk 2 more for farmers, Tk 4 for millers
Most Read
- Southwest engine explosion began when fan blade broke
- China wants to see smooth, stable elections in Bangladesh
- Soumya, Taskin, Imrul lose BCB contract, no pay hike for cricketers
- Saudi Arabia launches first new cinema, public showings start Friday
- Indian Prime Minister Modi confronted by angry protests in London
- Six Bangladeshi workers killed, another injured in Saudi fire
- Family faces uncertain future as Rashed’s death hits home
- Hasina seeks more investment in Bangladesh from top global business leaders
- UK Awami League demonstrates in London, demands Tarique’s extradition
- Condition of child labour inside Bangladesh’s bidi factories horrible, shocking: Study